News Updates

  • Recent!! Two Bailey Bridges have been erected (load capacity : 40 Ton)
  • Recent !! Project affected 18 households are successfully transfered into resettlement houses
  • Recent !! Vertical shaft 32 meter of Surge tank of Sanjen(Upper) Hydroelectric Project has been break through.
  • Latest News 4
  • Latest News 5

Status of the project

  • PPA was signed with NEA for SUHEP on 10 October, 2011 and for SHEP on 5 December, 2011.
  • The commercial operation date (COD) for SHUEP is July 2015 and for SHEP is December 2015.
  • Generation license for SHEP was received from the Ministry of Energy for a period of 35 years from 28 November 2011 and that for SUHEP was in 23 August 2012.
  • The Environmental Impact Assessment (EIA) reports of both the projects were approved by the Ministry of Environment.
  • Detailed project reports of both the projects are completed.
  • Debt portion of the project will be fully financed by EPF for which the tri-partite loan agreement were signed on 8 December,2011 between SJCL, Chilime and EPF.
  • Land acquisition and compensation distribution for the access road and project structures is completed.
  • Construction works of 10.65 km long main access road for the two projects are in progress.
  • 18.111 Hactare(356 ropani) of the land is provided for the construction of the infrastructure and the access road to both SUHEP and SHEP.
  • Construction of HeadWorks, Penstock Tunnel and Head race tunnel is in progress.
  • Construction of Headrace tunnel of the Sanjen(Upper) Hydroelectric project upto 490 meter is complete.
  • Excavation work of 50 meter long Aeration tunnel of the Sanjen (Upper) Hydroelectric project is complete.
  • Excavation work of the Adit Tunnel is completed upto 56m .
  • Fabrication work of the steel connection pipe is in progress of Sanjen Upper hydroelectric project
  • Fabrication work of the siphon pipe is in progress of Sanjen Hydroelectric project.
  • Construction of 11kv Construction power line is complete.
  • Design of Electromechanical(Lot - 3) and Hydromechanical (Lot - 4) works are in progress.
  • Detail study of 132 Kv transmission line is in progress.
  • Construction of residencial building and other required infrastructure of the project is almost complete.
  • Constructional work of Lot -1 is completed.
  • Works of Lot -2 ,Lot -3, Lot -4 and Lot -5 are under progress and are running parallely.